02/12/2024

36 seconds

Developments in the Construction in November – Waterside Residence

DSC_0346

We are already on the 4th floor with the masonry

02.12.2024.

Construction continued to progress dynamically at Waterside Residence in November.

The masonry of buildings ‘A’ and ‘D’ was completed on the 1st and 4th floors. The mechanical and electrical work on building ‘A’ is in progress and basic electrical and mechanical installation has started on building ‘D’.

On buildings ‘B’ and ‘C’, the 1st floor walls are finished. On ‘C’ building, the masonry work on the 2nd floor is already underway, which is also being has just started.

Would you like to follow the construction of your new home day by day? Follow our Youtube channel:

https://www.youtube.com/@IntergalGroup

Want a home with a panoramic view of the Danube? Ask for an individual offer from our colleagues:

📞+36 1 700 2500

✉️ sales@waterside.hu

More news

Request offer

First name*

Last name*

Phone*

E-mail*

Message

Selected apartments:

Thank you for getting in touch! 

We appreciate you contacting us about your future home in Waterside Residence. One of our sales managers will get back to you shortly.
Have a great day!